𝐒𝐋𝐁 𝐖𝐒𝐧𝐬 𝐌𝐚𝐣𝐨𝐫 𝐁𝐒𝐬𝐚𝐭 π„π±π©πšπ§π¬π’π¨π§ π‚π¨π§π­π«πšπœπ­ 𝐒𝐧 𝐎𝐦𝐚𝐧

oil gas • Sep 24, 2026
No image

SLB has secured a contract from OQ Exploration & Production (OQEP) to deliver the Bisat-B Expansion Production Facility in Oman. The project will cover design, engineering, procurement, construction and commissioning, followed by four years of operations and maintenance support.

The expansion is expected to increase the facility’s gross fluids handling capacity to 548,000 barrels per day, with completion targeted within 19 months. The project represents the next phase of development at the Bisat Field and builds on SLB’s earlier delivery of the Bisat-A facility in 2018 and the original Bisat-B facility in 2020.